Our planning uses DFW regional weather normals for heat and rain exposure. The regional climate normals average 20 days per year with temperatures reaching at least 100°F. We account for that prolonged heat when selecting gate operators and vinyl components and planning concrete placement. Material selection and the work sequence need to suit those conditions.
Spring rain changes excavation and post-setting plans. The regional May precipitation normal is 4.78 inches, so we assess drainage and ground moisture before digging and placing concrete. Wet ground affects the sequence of excavation, footing work and surface restoration around a new fence or gate pad.
Footing design follows our one-third depth rule. Where expansive black clay is present, swelling and shrinking can push shallow posts out of alignment and cause failures. We assess the soil at the property and account for drainage when planning concrete footings.